Washing Tower, Ø4000 mm × 25 m in SS 316L

At a glance: four washing towers in SS 316L, each 4,000 mm in diameter and 25 metres long, with trays. The original towers were imported and only partial drawings existed. Our scope covered completing the design, the tray internals, fabrication, hydro testing and delivery as single pieces. Four towers dispatched four months from order, then a 20-day over-dimensional move from Pune to Gujarat.

The requirement. A process plant in Gujarat uses washing towers to wash a product stream. New environmental regulations meant the plant had to add washing capacity, and it needed four more towers, each 4 metres across and 25 metres tall.

The plant's existing towers had been imported, and it placed the new order with two suppliers side by side: the original overseas supplier, and us. That put our towers in a direct comparison with the original maker's, on the same job and at the same time.

Working from partial drawings. The customer had only part of the original drawings. We completed the design from what was available and produced a full set of fabrication drawings for the shell and its internals, so the new towers would do the same job as the existing ones.

Designing and supplying the internals. The towers are fitted with trays. We designed the tray internals and supplied them with the towers, so the customer had a single supplier for the complete tower rather than a shell from us and internals from somewhere else.

One piece, 25 metres long. At 4 metres across and 25 metres long, each tower is one of the biggest single pieces we have built. Each was fabricated complete at our works in Pune, with no sections left to be joined at site.

Testing. Every tower was hydro tested at our works before dispatch.

Four towers in four months. All four towers were built and dispatched within four months of the order.

Getting them to Gujarat. A 25-metre, 4-metre-diameter tower is a super over-dimensional cargo (super ODC). Moving it means special trailers, a planned route, permissions from the road authorities and escorts. The journey from Pune to the plant in Gujarat took 20 days.

The result. The customer ordered the same towers from the original overseas supplier and from us, and could compare them side by side. Our quality and our cost were what impressed them.

Need a large column or tower built in one piece, or a second source for imported equipment? Send us what you have, even if the drawings are incomplete, and we will tell you how we would build and ship it.

Need this?

We fabricate in Titanium, Hastelloy, Inconel, Duplex and explosion-clad. Tell us the duty and we will engineer to it.